FY25-16 – NETCON Culvert Works

The Project

The FY25 NETCON Culvert Works project was a critical preventative maintenance program designed to prepare the Goonyella Rail Network for the wet weather season. Our team delivered targeted activities to minimise potential rainfall damage, ensuring effective water management and improved network resilience. By focusing on asset protection and corridor stability, we helped Aurizon maintain safer and more reliable rail operations throughout the peak storm season.
Client
Aurizon
Value
Duration
FY25 (Nov-Dec 2024)
Location
Goonyella Rail Network, Central Queensland
Services
Rail infrastructure maintenance, wet weather preparedness, and civil construction

The Scope

  • Successfully completed a high-intensity drainage maintenance program across the Goonyella system
  • Restored optimal water flow by removing silt build-up for 10 metres on either side of culvert structures
  • Utilised vacuum-truck technology to clear inlets and outlets of internal debris and blockages
  • Improved waterway efficiency by de-grassing and removing large debris from flood-prone areas
  • Reinforced embankments through the installation and repair of scour and batter protection
  • Restored safe maintenance access by repairing and grading corridor entry tracks
  • Rectified pipe misalignments to ensure fully functional drainage across all project sites
  • Delivered the project ahead of schedule to ensure the network was protected before the first seasonal rains
  • Facilitated private land access through effective community engagement and stakeholder management
  • Maintained a perfect safety record while delivering works on budget and ahead of time

Other Schwarz Projects

Aurizon – BW-03-006 – Culvert Package – Sleeper Causeways

Aurizon – Blackwater Drainage Package (Multiple Sites)

Aurizon – Newlands & Goonyella Bridge Signage Package

Explore all our works

Let's chat about your project

This website uses cookies for analytics and to improve web experience.